As part of their ongoing City-wide fiber optic network installation, Netly, LLC, will be paving over the trench work they performed in Lomas Santa Fe, surrounding and below the Interstate 5 (I-5) interchange. Due to the high volume of traffic on Lomas Santa Fe and the I-5 Freeway ramps, construction work for this part of the work will be conducted at night.
This night-time work will take place during two (2) nights on July 15 and July 16 between the hours of 7:00 PM and 5:00 AM. All traffic lanes will be operational by 6:00 AM the following morning, well before morning peak hour traffic.
Construction of Phase 1 of this 17-phase project started in January 2020 and was completed in mid-March 2020. Construction of Phase 2 began the first week of March 2020 and is expected to be completed in early July. Construction in Phase 3 will start in early July and is expected to be completed in mid-August. The limits of each phase are shown on the attached map.
If you have any questions or comments regarding the project or the specific construction work, please contact the City of Solana Beach
Engineering Department at 858.720.2470.